Dept. of Trans. SEMI-FINAL Serial No. Contract No. 09-120-06-19 06-0G3104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-FRE-180-127.0/137.0 Federal Project: NONE Progress payment No. 06 Payment period ending: 04-02-09 CORAL CONSTRUCTION COMPANY P O BOX 347 WILSONVILLE OR 97070 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 736,946.25 4,272.50 2.a. Extra Work 39,044.37 12,690.06 b. Adjustment Comp. -1,274.22 -1,274.22 3. Materials on Hand 4. Earned Subject to Retention 774,716.40 15,688.34 5. Mobilization 95,000.00 0.00 6. Total Work Completed 869,716.40 7. Deductions -20,000.00 0.00 8. a.Contract Retentions -36,064.38 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 36,064.38 0.00 9. Total pay to Contractor 849,716.40 15,688.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 15,688.34