Dept. of Trans. PROGRESS Serial No. Contract No. 11-266-05-48 06-0G4604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 23% 82% 06-FRE-5-1.7/62.2 Federal Project: 06-FRE-33-R39.8/ .0 NONE Progress payment No. 01 Payment period ending: 09-20-11 VICTORY ENGINEERS INC 10266 HIGHWAY 41 MADERA CA 93636 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 87,944.07 87,944.07 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 87,944.07 87,944.07 5. Mobilization 25,799.50 25,799.50 6. Total Work Completed 113,743.57 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. -8,794.41 -8,794.41 c. Reduction after 95% Comp. 9. Total pay to Contractor 104,949.16 104,949.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 104,949.16