Dept. of Trans. PROGRESS Serial No. Contract No. 21-141-14-03 06-0G8514 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 100% Location: Federal Project: 06-KER-58-R52.7/R55.5 ACNH-P058(128) Progress payment No. 028 Payment period ending: 05-20-21 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,943,562.17 235,598.85 2. a. Extra Work 276,605.10 44,177.45 b. Adustment Comp. -40,777.26 0.00 3. Materials on Hand 4. Earned Subject to Retention 20,179,390.01 279,776.30 5. Mobilization 1,274,000.00 0.00 6. Total Work Completed 21,453,390.01 7. Deductions -404,715.90 5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 21,048,674.11 284,776.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 284,776.30