Dept. of Trans. SEMI-FINAL Serial No. Contract No. 21-301-13-09 06-0G8514 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 06-KER-58-R52.7/R55.5 ACNH-P058(128) Progress payment No. 032 Payment period ending: 09-30-21 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,113,265.82 -32,000.00 2. a. Extra Work 466,623.22 30,665.10 b. Adustment Comp. -40,777.26 0.00 3. Materials on Hand 4. Earned Subject to Retention 20,539,111.78 -1,334.90 5. Mobilization 1,274,000.00 0.00 6. Total Work Completed 21,813,111.78 7. Deductions -658,762.09 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 21,154,349.69 -1,334.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -1,334.90