Dept. of Trans. PROGRESS Serial No. Contract No. 16-022-11-56 06-0G9004 PROGRESS PAYMENT VOUCHER %complete: %time: 2% 0% Location: Federal Project: 06-MAD-41-11.7/13.4 NHP-P041(128) Progress payment No. 001 Payment period ending: 01-20-16 A. TEICHERT & SON INC. DBA TEICHERT CONSTRUCTION 5771 S. TOYOTA AVE FRESNO CA 93725 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 197,109.60 197,109.60 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 197,109.60 197,109.60 5. Mobilization 6. Total Work Completed 197,109.60 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 197,109.60 197,109.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 197,109.60