Dept. of Trans. PROGRESS Serial No. Contract No. 13-295-06-41 06-0H1804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 18% 20% 06-KER-14-39.3/40.3 Federal Project: BRNH-P014(72) Progress payment No. 03 Payment period ending: 10-20-13 GRANITE CONSTRUCTION COMPANY P O BOX 5127 BAKERFIELD CA 93388 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 714,958.28 406,170.00 2.a. Extra Work 52,139.90 52,139.90 b. Adjustment Comp. 3. Materials on Hand 520,474.30 520,474.30 4. Earned Subject to Retention 1,287,572.48 978,784.20 5. Mobilization 641,250.00 641,250.00 6. Total Work Completed 1,408,348.18 7. Deductions -57,167.57 -57,167.57 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,871,654.91 1,562,866.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,562,866.63