Dept. of Trans. PROGRESS Serial No. Contract No. 14-265-10-20 06-0H1804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 80% 85% 06-KER-14-39.3/40.3 Federal Project: BRNH-P014(72) Progress payment No. 13 Payment period ending: 09-20-14 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES, CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,648,465.53 794,482.40 2.a. Extra Work 440,242.49 30,025.41 b. Adjustment Comp. 36,193.20 0.00 3. Materials on Hand 107,446.16 -55,275.50 4. Earned Subject to Retention 6,232,347.38 769,232.31 5. Mobilization 855,000.00 0.00 6. Total Work Completed 6,979,901.22 7. Deductions -70,890.10 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,016,457.28 769,232.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 769,232.31