Dept. of Trans. PROGRESS Serial No. Contract No. 14-323-09-14 06-0H1804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 95% 06-KER-14-39.3/40.3 Federal Project: BRNH-P014(72) Progress payment No. 15 Payment period ending: 11-20-14 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES, CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,632,827.53 820,122.00 2.a. Extra Work 501,260.66 0.00 b. Adjustment Comp. 36,193.20 0.00 3. Materials on Hand 0.00 -55,520.41 4. Earned Subject to Retention 7,170,281.39 764,601.59 5. Mobilization 855,000.00 0.00 6. Total Work Completed 8,025,281.39 7. Deductions -76,255.10 -3,615.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,949,026.29 760,986.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 760,986.59