Dept. of Trans. FINAL Serial No. Contract No. 10-067-09-46 06-0H2704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-MAD-41-3.3/5.3 Federal Project: ACHS-P041(108) NH-P041(108) Progress payment No. 08 Payment period ending: 12-14-09 CRUCO CONSTRUCTION GROUP INC 2443 FOUNDRY PARK AVENUE FRESNO CA 93706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,031,472.33 0.00 2.a. Extra Work 19,949.47 0.00 b. Adjustment Comp. 282,155.48 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,333,577.28 0.00 5. Mobilization 10,000.00 0.00 6. Total Work Completed 1,343,577.28 7. Deductions 0.00 13,793.80 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,343,577.28 13,793.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 13,793.80