Dept. of Trans. PROGRESS Serial No. Contract No. 09-294-07-56 06-0H7104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 13% 58% 06-TUL-65-23.4/25.1 Federal Project: NONE Progress payment No. 01 Payment period ending: 10-20-09 MIDSTATE BARRIER INC P O BOX 30550 STOCKTON CA 952130550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 44,942.00 44,942.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 44,942.00 44,942.00 5. Mobilization 6. Total Work Completed 44,942.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 44,942.00 44,942.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 44,942.00