Dept. of Trans. PROGRESS Serial No. Contract No. 10-264-07-11 06-0H7404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 24% 62% 06-KIN-198-R19.0/T21.7 Federal Project: ACHS-P198(53) NHG-P198(53) Progress payment No. 02 Payment period ending: 09-20-10 BUSH ENGINEERING INC 518 N REDINGTON STREET HANFORD CA 93230 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 284,763.82 225,768.34 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 284,763.82 225,768.34 5. Mobilization 80,250.00 80,250.00 6. Total Work Completed 365,013.82 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 365,013.82 306,018.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 306,018.34