Dept. of Trans. PROGRESS Serial No. Contract No. 12-024-07-51 06-0H8304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 74% 98% 06-KER-184-1.0/ .0 Federal Project: ACST-P184(14) P-P184(14) Progress payment No. 03 Payment period ending: 01-20-12 PTM GENERAL ENGINEERING SERVICES INC P O BOX 7745 RIVERSIDE CA 92513 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 332,082.25 73,567.92 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 332,082.25 73,567.92 5. Mobilization 6. Total Work Completed 332,082.25 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. -29,409.61 -7,356.79 c. Reduction after 95% Comp. 9. Total pay to Contractor 292,672.64 56,211.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 56,211.13