Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 13-037-07-24 06-0J0504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-KIN-43-24.2/24.7 Federal Project: ACHS-P043(40) STP Progress payment No. 06 Payment period ending: 01-18-13 GRIFFITH COMPANY 1128 CARRIER PARKWAY AVENUE BAKERSFIELD, CA 93308 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 733,089.75 32.40 2.a. Extra Work 16,897.31 16,897.31 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 749,987.06 16,929.71 5. Mobilization 68,573.50 0.00 6. Total Work Completed 818,560.56 7. Deductions -123,600.00 28,900.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 694,960.56 45,829.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 45,829.71