Dept. of Trans. PROGRESS Serial No. Contract No. 08-269-07-07 06-0J4504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 98% 100% 06-MAD-41-20.9/32.9 Federal Project: NONE Progress payment No. 02 Payment period ending: 09-20-08 INTERNATIONAL SURFACING SYSTEMS P O BOX 4770 MODESTO CA 95352 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 932,533.68 663,572.43 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 932,533.68 663,572.43 5. Mobilization 6. Total Work Completed 932,533.68 7. Deductions -58,994.72 -45,548.91 8. a.Contract Retentions -46,626.68 -29,194.82 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 826,912.28 588,828.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 588,828.70