Dept. of Trans. PROGRESS Serial No. Contract No. 12-332-09-19 06-0J5204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 24% 81% 06-KER-119-4.7/8.5 Federal Project: ACHS-STP(15) P119(15) Progress payment No. 03 Payment period ending: 11-20-12 GRIFFITH COMPANY 1128 CARRIER PARKWAY AVE BAKERSFIELD CA 93308 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 547,217.70 209,376.70 2.a. Extra Work 15,685.81 15,685.81 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 562,903.51 225,062.51 5. Mobilization 175,500.00 0.00 6. Total Work Completed 738,403.51 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. -22,506.25 -22,506.25 c. Reduction after 95% Comp. 9. Total pay to Contractor 715,897.26 202,556.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 202,556.26