Dept. of Trans. PROGRESS Serial No. Contract No. 16-113-15-19 06-0J5304 PROGRESS PAYMENT VOUCHER %complete: %time: 7% 5% Location: Federal Project: 06-TUL-190-20.9/21.2 SSTP-P190(20) SIPL-6206(23) Progress payment No. 003 Payment period ending: 04-20-16 LEE'S PAVING INC 1212 N PLAZA DR VISALIA CA 93291 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 128,044.75 109,673.75 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 128,044.75 109,673.75 5. Mobilization 62,800.00 62,800.00 6. Total Work Completed 190,844.75 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 190,844.75 172,473.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 172,473.75