Dept. of Trans. PROGRESS Serial No. Contract No. 14-324-14-04 06-0J9204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 34% 06-FRE-145-32.8/33.4 Federal Project: SSTP-P145(31) Progress payment No. 07 Payment period ending: 11-20-14 RSB GROUP INC 20331 LAKE FORREST DRIVE C13 LAKE FORREST CA 92630 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,059,713.30 111,736.64 2.a. Extra Work 73,663.86 43,821.53 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,133,377.16 155,558.17 5. Mobilization 185,770.00 0.00 6. Total Work Completed 1,319,147.16 7. Deductions -130,927.39 -33,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,188,219.77 122,558.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 122,558.17