Dept. of Trans. PROGRESS Serial No. Contract No. 13-238-08-52 06-0K3904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 45% 43% 06-KER-58-R99.3/R99.7 Federal Project: NH-P058(114) Progress payment No. 05 Payment period ending: 08-20-13 AMERICAN PAVING CO P O BOX 4348 FRESNO CA 93744 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 638,153.69 278,483.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 638,153.69 278,483.00 5. Mobilization 88,350.00 0.00 6. Total Work Completed 726,503.69 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 716,503.69 268,483.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 268,483.00