Dept. of Trans. PROGRESS Serial No. Contract No. 13-263-05-39 06-0K3904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 47% 69% 06-KER-58-R99.3/R99.7 Federal Project: NH-P058(114) Progress payment No. 06 Payment period ending: 09-20-13 AMERICAN PAVING CO P O BOX 4348 FRESNO CA 93744 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 662,615.69 24,462.00 2.a. Extra Work 8,610.47 8,610.47 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 671,226.16 33,072.47 5. Mobilization 88,350.00 0.00 6. Total Work Completed 759,576.16 7. Deductions -20,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 739,576.16 23,072.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 23,072.47