Dept. of Trans. FINAL Serial No. Contract No. 13-011-06-06 06-0K4504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-KER-14-15.3/ .0 Federal Project: NONE Progress payment No. 04 Payment period ending: 11-08-12 AUTOBAHN CONSTRUCTION INC P O BOX 11238 SANTA ANA CA 927111238 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 467,000.00 5,856.50 2.a. Extra Work 33,471.25 29,971.25 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 500,471.25 35,827.75 5. Mobilization 50,000.00 0.00 6. Total Work Completed 550,471.25 7. Deductions 0.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 550,471.25 45,827.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 45,827.75