Dept. of Trans. PROGRESS Serial No. Contract No. 18-232-11-23 06-0K4604 PROGRESS PAYMENT VOUCHER %complete: %time: 68% 51% Location: Federal Project: 06-KER-46-57.3/57.8 ACNH-X029(129) 06-KER-99-43.9/44.6 Progress payment No. 015 Payment period ending: 08-20-18 SEMA CONSTRUCTION INC 320 GODDARD WAY #150 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,257,074.62 1,166,558.32 2. a. Extra Work 233,078.09 24,618.46 b. Adustment Comp. 381,046.33 12,559.03 3. Materials on Hand 38,226.63 -327,173.37 4. Earned Subject to Retention 8,909,425.67 876,562.44 5. Mobilization 1,431,957.65 0.00 6. Total Work Completed 10,303,156.69 7. Deductions -326,942.04 -288,107.45 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,014,441.28 588,454.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 588,454.99