Dept. of Trans. PROGRESS Serial No. Contract No. 18-292-09-57 06-0K4604 PROGRESS PAYMENT VOUCHER %complete: %time: 73% 59% Location: Federal Project: 06-KER-46-57.3/57.8 ACNH-X029(129) 06-KER-99-43.9/44.6 Progress payment No. 017 Payment period ending: 10-20-18 SEMA CONSTRUCTION INC 320 GODDARD WAY #150 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,109,207.16 504,013.25 2. a. Extra Work 234,578.09 0.00 b. Adustment Comp. 381,046.33 0.00 3. Materials on Hand 24,665.00 0.00 4. Earned Subject to Retention 9,749,496.58 504,013.25 5. Mobilization 1,431,957.65 0.00 6. Total Work Completed 11,156,789.23 7. Deductions -179,837.59 -131,003.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,001,616.64 373,010.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 373,010.25