Dept. of Trans. FINAL Serial No. Contract No. 20-261-09-33 06-0K4604 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 06-KER-46-57.3/57.8 ACNH-X029(129) 06-KER-99-43.9/44.6 Progress payment No. 035 Payment period ending: 08-26-19 SEMA CONSTRUCTION INC 42690 RIO NEDO #G TEMECULA CA 92590 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,145,679.71 0.00 2. a. Extra Work 922,243.35 0.00 b. Adustment Comp. 792,748.77 65,202.99 3. Materials on Hand 4. Earned Subject to Retention 14,860,671.83 65,202.99 5. Mobilization 1,431,957.65 0.00 6. Total Work Completed 16,292,629.48 7. Deductions -16,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,276,629.48 65,202.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 65,202.99