Dept. of Trans. PROGRESS Serial No. Contract No. 11-054-07-36 06-0K4704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 67% 06-KER-178-100.1/101.6 Federal Project: NONE Progress payment No. 05 Payment period ending: 02-20-11 TENNYSON ELECTRIC INC 7275 NATIONAL DRIVE SUITE A2 LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 263,811.94 27,621.50 2.a. Extra Work 13,663.43 4,805.52 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 277,475.37 32,427.02 5. Mobilization 6. Total Work Completed 277,475.37 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 277,475.37 32,427.02 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 32,427.02