Dept. of Trans. PROGRESS Serial No. Contract No. 10-355-11-50 06-0K6804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 67% 100% 06-KER-43-25.1/38.8 Federal Project: NONE Progress payment No. 03 Payment period ending: 12-20-10 INTERNATIONAL SURFACING SYSTEMS P O BOX 4770 MODESTO CA 95352 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 866,155.31 270,657.04 2.a. Extra Work 114,840.55 114,840.55 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 980,995.86 385,497.59 5. Mobilization 6. Total Work Completed 980,995.86 7. Deductions -28,569.00 -14,769.00 8. a.Contract Retentions b. Unsatisfactory Prog. -97,123.74 -38,549.76 c. Reduction after 95% Comp. 9. Total pay to Contractor 855,303.12 332,178.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 332,178.83