Dept. of Trans. PROGRESS Serial No. Contract No. 17-202-12-13 06-0K8004 PROGRESS PAYMENT VOUCHER %complete: %time: 16% 0% Location: Federal Project: 06-FRE-33-0.0 STP-000C(442) Progress payment No. 006 Payment period ending: 07-20-17 VIKING CONSTRUCTION CO INC PO BOX 1508 RANCHO CORDOVA CA 95741-1508 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 199,850.00 0.00 2. a. Extra Work 8,056.12 8,056.12 b. Adustment Comp. 3. Materials on Hand 145,583.18 145,583.18 4. Earned Subject to Retention 353,489.30 153,639.30 5. Mobilization 174,225.00 58,075.00 6. Total Work Completed 382,131.12 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 517,714.30 211,714.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 211,714.30