Dept. of Trans. PROGRESS Serial No. Contract No. 17-360-14-47 06-0K8004 PROGRESS PAYMENT VOUCHER %complete: %time: 39% 0% Location: Federal Project: 06-FRE-33-0.0 STP-000C(442) Progress payment No. 009 Payment period ending: 12-20-17 VIKING CONSTRUCTION CO INC PO BOX 1508 RANCHO CORDOVA CA 95741-1508 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 651,802.50 419,430.00 2. a. Extra Work 21,414.75 11,902.84 b. Adustment Comp. 3. Materials on Hand 5,701.29 -340,780.33 4. Earned Subject to Retention 678,918.54 90,552.51 5. Mobilization 220,685.00 0.00 6. Total Work Completed 893,902.25 7. Deductions 0.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 899,603.54 100,552.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 100,552.51