Dept. of Trans. PROGRESS Serial No. Contract No. 18-079-09-44 06-0K8004 PROGRESS PAYMENT VOUCHER %complete: %time: 68% 30% Location: Federal Project: 06-FRE-33-0.0 STP-000C(442) Progress payment No. 012 Payment period ending: 03-20-18 VIKING CONSTRUCTION CO INC PO BOX 1508 RANCHO CORDOVA CA 95741-1508 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,360,311.50 137,038.30 2. a. Extra Work 50,802.73 7,560.94 b. Adustment Comp. -62,607.25 0.00 3. Materials on Hand 33,358.92 0.00 4. Earned Subject to Retention 1,381,865.90 144,599.24 5. Mobilization 232,300.00 0.00 6. Total Work Completed 1,580,806.98 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,614,165.90 144,599.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 144,599.24