Dept. of Trans. PROGRESS Serial No. Contract No. 18-114-12-06 06-0K8004 PROGRESS PAYMENT VOUCHER %complete: %time: 80% 45% Location: Federal Project: 06-FRE-33-0.0 STP-000C(442) Progress payment No. 013 Payment period ending: 04-20-18 VIKING CONSTRUCTION CO INC PO BOX 1508 RANCHO CORDOVA CA 95741-1508 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,641,797.30 281,485.80 2. a. Extra Work 50,802.73 0.00 b. Adustment Comp. -62,607.25 0.00 3. Materials on Hand 27,657.63 -5,701.29 4. Earned Subject to Retention 1,657,650.41 275,784.51 5. Mobilization 232,300.00 0.00 6. Total Work Completed 1,862,292.78 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,889,950.41 275,784.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 275,784.51