Dept. of Trans. PROGRESS Serial No. Contract No. 18-171-13-25 06-0K8004 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 72% Location: Federal Project: 06-FRE-33-0.0 STP-000C(442) Progress payment No. 015 Payment period ending: 06-20-18 VIKING CONSTRUCTION CO INC PO BOX 1508 RANCHO CORDOVA CA 95741-1508 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,961,425.50 241,082.75 2. a. Extra Work 76,032.03 25,229.30 b. Adustment Comp. -62,607.25 0.00 3. Materials on Hand 27,657.63 0.00 4. Earned Subject to Retention 2,002,507.91 266,312.05 5. Mobilization 232,300.00 0.00 6. Total Work Completed 2,207,150.28 7. Deductions -3,950.00 -3,950.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,230,857.91 262,362.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 262,362.05