Dept. of Trans. PROGRESS Serial No. Contract No. 11-265-08-30 06-0K8904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 40% 84% 06-KER-5-36.1/54.2 Federal Project: IM-SARR(A00) Progress payment No. 06 Payment period ending: 09-20-11 GIFFITH COMPANY 1128 CARRIER PARKWAY AVENUE BAKERSFIELD CA 93308 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,850,754.19 2,248,071.24 2.a. Extra Work 44,911.67 7,988.19 b. Adjustment Comp. 217,041.73 0.00 3. Materials on Hand 4. Earned Subject to Retention 9,112,707.59 2,256,059.43 5. Mobilization 3,581,615.90 0.00 6. Total Work Completed 12,694,323.49 7. Deductions -695,623.34 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. -225,605.94 -225,605.94 c. Reduction after 95% Comp. 9. Total pay to Contractor 11,773,094.21 2,030,453.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,030,453.49