Dept. of Trans. PROGRESS Serial No. Contract No. 11-355-06-37 06-0K8904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 50% 98% 06-KER-5-36.1/54.2 Federal Project: IM-SARR(A00) Progress payment No. 09 Payment period ending: 12-20-11 GIFFITH COMPANY 1128 CARRIER PARKWAY AVENUE BAKERSFIELD CA 93308 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,669,827.76 69,347.75 2.a. Extra Work 119,967.37 39,950.68 b. Adjustment Comp. 575,787.86 358,746.13 3. Materials on Hand 23,795.52 23,795.52 4. Earned Subject to Retention 12,389,378.51 491,840.08 5. Mobilization 3,581,615.90 0.00 6. Total Work Completed 15,947,198.89 7. Deductions -695,623.34 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. -553,273.03 -49,184.01 c. Reduction after 95% Comp. 9. Total pay to Contractor 14,722,098.04 442,656.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 442,656.07