Dept. of Trans. PROGRESS Serial No. Contract No. 12-263-06-57 06-0L0504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 9% 4% 06-KIN-198-R21.5/R28.3 Federal Project: 06-TUL-198-0.0/R3.4 ACNH-P198(59) Progress payment No. 01 Payment period ending: 09-20-12 WABO LANDSCAPE & CONSTRUCTION INC 726 ALFRED NOBEL DRIVE HERCULES CA 94547 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 110,307.44 110,307.44 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 89,494.30 89,494.30 4. Earned Subject to Retention 199,801.74 199,801.74 5. Mobilization 6. Total Work Completed 110,307.44 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 199,801.74 199,801.74 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 199,801.74