Dept. of Trans. PROGRESS Serial No. Contract No. 12-331-09-07 06-0L0504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 55% 15% 06-KIN-198-R21.5/R28.3 Federal Project: 06-TUL-198-0.0/R3.4 ACNH-P198(59) Progress payment No. 03 Payment period ending: 11-20-12 WABO LANDSCAPE & CONSTRUCTION INC 726 ALFRED NOBEL DRIVE HERCULES CA 94547 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 708,138.86 154,825.96 2.a. Extra Work b. Adjustment Comp. -2,812.29 -2,812.29 3. Materials on Hand 52,510.00 -3,990.60 4. Earned Subject to Retention 757,836.57 148,023.07 5. Mobilization 6. Total Work Completed 705,326.57 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 757,836.57 148,023.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 148,023.07