Dept. of Trans. PROGRESS Serial No. Contract No. 12-205-10-28 06-0L6404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 25% 25% 06-KER-99-R28.4/R43.9 Federal Project: ACNH-P099(551) Progress payment No. 04 Payment period ending: 07-20-12 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,691,329.20 3,887,884.36 2.a. Extra Work b. Adjustment Comp. -10,004.28 -10,004.28 3. Materials on Hand 4. Earned Subject to Retention 15,681,324.92 3,877,880.08 5. Mobilization 5,850,000.00 0.00 6. Total Work Completed 21,531,324.92 7. Deductions -3,000.00 -3,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 21,528,324.92 3,874,880.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,874,880.08