Dept. of Trans. PROGRESS Serial No. Contract No. 12-235-07-03 06-0L6404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 33% 31% 06-KER-99-R28.4/R43.9 Federal Project: ACNH-P099(551) Progress payment No. 05 Payment period ending: 08-20-12 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 20,977,279.72 5,285,950.52 2.a. Extra Work b. Adjustment Comp. -89,029.34 -79,025.06 3. Materials on Hand 378,667.54 378,667.54 4. Earned Subject to Retention 21,266,917.92 5,585,593.00 5. Mobilization 7,410,000.00 1,560,000.00 6. Total Work Completed 28,298,250.38 7. Deductions -1,329,487.63 -1,326,487.63 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 27,347,430.29 5,819,105.37 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,819,105.37