Dept. of Trans. PROGRESS Serial No. Contract No. 12-262-07-06 06-0L6404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 39% 40% 06-KER-99-R28.4/R43.9 Federal Project: ACNH-P099(551) Progress payment No. 06 Payment period ending: 09-20-12 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 26,447,016.45 5,469,736.73 2.a. Extra Work b. Adjustment Comp. -153,069.13 -64,039.79 3. Materials on Hand 201,757.68 -176,909.86 4. Earned Subject to Retention 26,495,705.00 5,228,787.08 5. Mobilization 7,410,000.00 0.00 6. Total Work Completed 33,703,947.32 7. Deductions -1,326,487.63 3,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 32,579,217.37 5,231,787.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,231,787.08