Dept. of Trans. PROGRESS Serial No. Contract No. 12-297-07-41 06-0L6404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 45% 48% 06-KER-99-R28.4/R43.9 Federal Project: ACNH-P099(551) Progress payment No. 07 Payment period ending: 10-20-12 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 31,345,701.21 4,898,684.76 2.a. Extra Work b. Adjustment Comp. -156,491.73 -3,422.60 3. Materials on Hand 302,636.52 100,878.84 4. Earned Subject to Retention 31,491,846.00 4,996,141.00 5. Mobilization 7,410,000.00 0.00 6. Total Work Completed 38,599,209.48 7. Deductions -5,000.00 1,321,487.63 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 38,896,846.00 6,317,628.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,317,628.63