Dept. of Trans. PROGRESS Serial No. Contract No. 12-331-09-19 06-0L6404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 51% 56% 06-KER-99-R28.4/R43.9 Federal Project: ACNH-P099(551) Progress payment No. 08 Payment period ending: 11-20-12 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 36,908,749.85 5,563,048.64 2.a. Extra Work b. Adjustment Comp. -166,813.04 -10,321.31 3. Materials on Hand 0.00 -302,636.52 4. Earned Subject to Retention 36,741,936.81 5,250,090.81 5. Mobilization 7,410,000.00 0.00 6. Total Work Completed 44,151,936.81 7. Deductions -5,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 44,146,936.81 5,250,090.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,250,090.81