Dept. of Trans. PROGRESS Serial No. Contract No. 12-355-09-57 06-0L6404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 58% 61% 06-KER-99-R28.4/R43.9 Federal Project: ACNH-P099(551) Progress payment No. 09 Payment period ending: 12-20-12 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 42,157,401.19 5,248,651.34 2.a. Extra Work b. Adjustment Comp. -166,813.04 0.00 3. Materials on Hand 33,600.00 33,600.00 4. Earned Subject to Retention 42,024,188.15 5,282,251.34 5. Mobilization 7,800,000.00 390,000.00 6. Total Work Completed 49,790,588.15 7. Deductions -5,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 49,819,188.15 5,672,251.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,672,251.34