Dept. of Trans. PROGRESS Serial No. Contract No. 13-023-07-14 06-0L6404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 61% 58% 06-KER-99-R28.4/R43.9 Federal Project: ACNH-P099(551) Progress payment No. 10 Payment period ending: 01-20-13 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 44,780,523.34 2,623,122.15 2.a. Extra Work b. Adjustment Comp. -166,813.04 0.00 3. Materials on Hand 33,600.00 0.00 4. Earned Subject to Retention 44,647,310.30 2,623,122.15 5. Mobilization 7,800,000.00 0.00 6. Total Work Completed 52,413,710.30 7. Deductions -5,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 52,442,310.30 2,623,122.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,623,122.15