Dept. of Trans. PROGRESS Serial No. Contract No. 13-056-10-34 06-0L6404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 64% 58% 06-KER-99-R28.4/R43.9 Federal Project: ACNH-P099(551) Progress payment No. 11 Payment period ending: 02-20-13 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 47,641,269.58 2,860,746.24 2.a. Extra Work 1,195.71 1,195.71 b. Adjustment Comp. -126,114.50 40,698.54 3. Materials on Hand 33,600.00 0.00 4. Earned Subject to Retention 47,549,950.79 2,902,640.49 5. Mobilization 7,800,000.00 0.00 6. Total Work Completed 55,316,350.79 7. Deductions -725,186.56 -720,186.56 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 54,624,764.23 2,182,453.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,182,453.93