Dept. of Trans. PROGRESS Serial No. Contract No. 13-081-11-13 06-0L6404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 64% 62% 06-KER-99-R28.4/R43.9 Federal Project: ACNH-P099(551) Progress payment No. 13 Payment period ending: 03-20-13 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 47,765,452.10 124,182.52 2.a. Extra Work 9,545.73 8,350.02 b. Adjustment Comp. -130,867.76 -4,753.26 3. Materials on Hand 0.00 -33,600.00 4. Earned Subject to Retention 47,644,130.07 94,179.28 5. Mobilization 7,800,000.00 0.00 6. Total Work Completed 55,444,130.07 7. Deductions -10,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 55,434,130.07 94,179.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 94,179.28