Dept. of Trans. PROGRESS Serial No. Contract No. 13-203-18-55 06-0L6404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 77% 80% 06-KER-99-R28.4/R43.9 Federal Project: ACNH-P099(551) Progress payment No. 17 Payment period ending: 07-20-13 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 58,098,286.97 1,869,259.40 2.a. Extra Work 16,441.08 6,895.35 b. Adjustment Comp. -122,187.82 425.50 3. Materials on Hand 4. Earned Subject to Retention 57,992,540.23 1,876,580.25 5. Mobilization 7,800,000.00 0.00 6. Total Work Completed 65,792,540.23 7. Deductions -475,314.85 -467,314.85 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 65,317,225.38 1,409,265.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,409,265.40