Dept. of Trans. PROGRESS Serial No. Contract No. 14-022-07-23 06-0L6404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 88% 100% 06-KER-99-R28.4/R43.9 Federal Project: ACNH-P099(551) Progress payment No. 23 Payment period ending: 01-20-14 SECURITY PAVING COMPANY INC 13170 TELFAIR AVE SYLMAR CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 68,379,992.71 78,805.03 2.a. Extra Work 376,231.89 8,753.57 b. Adjustment Comp. 529,535.67 0.00 3. Materials on Hand 4. Earned Subject to Retention 69,285,760.27 87,558.60 5. Mobilization 7,800,000.00 0.00 6. Total Work Completed 77,085,760.27 7. Deductions -23,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 77,062,760.27 77,558.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 77,558.60