Dept. of Trans. PROGRESS Serial No. Contract No. 17-053-11-13 06-0M2504 PROGRESS PAYMENT VOUCHER %complete: %time: 26% 29% Location: Federal Project: 06-FRE-198-35.3/35.6 ACNH-PP19-8(70) Progress payment No. 003 Payment period ending: 02-20-17 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 434,874.14 155,076.14 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4,510.75 4,510.75 4. Earned Subject to Retention 439,384.89 159,586.89 5. Mobilization 168,750.00 0.00 6. Total Work Completed 603,624.14 7. Deductions 0.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 608,134.89 169,586.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 169,586.89