Dept. of Trans. PROGRESS Serial No. Contract No. 16-078-09-33 06-0M2604 PROGRESS PAYMENT VOUCHER %complete: %time: 71% 65% Location: Federal Project: 06-KER-58-R99.2/R99.8 NHP-P058(122) Progress payment No. 005 Payment period ending: 03-20-16 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,254,109.17 377,873.62 2. a. Extra Work b. Adustment Comp. -3,000.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,251,109.17 377,873.62 5. Mobilization 65,000.00 3,250.00 6. Total Work Completed 1,316,109.17 7. Deductions -1,500.00 -1,500.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,314,609.17 379,623.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 379,623.62