Dept. of Trans. SEMI-FINAL Serial No. Contract No. 11-353-10-59 06-0M3004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-KER-178-15.7/26.4 Federal Project: NONE Progress payment No. 05 Payment period ending: 11-17-11 MICHELS PIPELINE CONSTRUCTION P O BOX 12905 SALEM OR 97309 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 378,522.00 0.00 2.a. Extra Work 13,188.82 13,188.82 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 391,710.82 13,188.82 5. Mobilization 6. Total Work Completed 391,710.82 7. Deductions -10,000.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 381,710.82 23,188.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 23,188.82