Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 11-270-06-25 06-0M3204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-KER-178-30.4/41.6 Federal Project: NONE Progress payment No. 03 Payment period ending: 09-14-11 MARTIN BROTHERS CONSTRUCTION 20 LIGHT SKY COURT SACRAMENTO CA 95828 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 541,888.81 38,761.10 2.a. Extra Work b. Adjustment Comp. -4,212.98 -4,212.98 3. Materials on Hand 4. Earned Subject to Retention 537,675.83 34,548.12 5. Mobilization 6. Total Work Completed 537,675.83 7. Deductions -10,000.00 37,500.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 527,675.83 72,048.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 72,048.12