Dept. of Trans. PROGRESS Serial No. Contract No. 17-264-11-13 06-0M3704 PROGRESS PAYMENT VOUCHER %complete: %time: 86% 83% Location: Federal Project: 06-KIN-43-1.3/1.7 HSST-P 06-KIN-137-0.0/0.2 P043-046(E) Progress payment No. 005 Payment period ending: 09-20-17 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,609,189.10 227,515.20 2. a. Extra Work b. Adustment Comp. -23,227.15 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,585,961.95 227,515.20 5. Mobilization 317,184.00 0.00 6. Total Work Completed 2,903,145.95 7. Deductions -3,000.00 7,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,900,145.95 234,515.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 234,515.20